Page 332 - Anuario FFCC - 2026
P. 332
company guide facilities will be modified so that the standard interoperable PREPARATION OF THE PROJECT FOR THE CONSTRUC-
train length (750 m) can be used.
TION OF THE MADRID-EXTREMADURA-PORTUGUESE
BORDER HIGH SPEED LINE. SECTION: TALAYUELA-PLA-
SENCIA
The works will be carried out in a joint venture with Prointec
and E2F in two phases, the first of which will be dedicated to
The subject of the contract is the construction of a conven-
the preliminary works for the preparation of the new platform,
the new station platforms and the extension of the drainage
tional gauge double track mixed traffic high speed line in the
province of Cáceres, including the following main activities:
works, while the second and main phase will focus on the
change of gauge and the adaptation of the catenary.
Talayuela to Plasencia, over a length of approximately 70 km.
ASSISTANCE AND CONTROL OF THE CONSTRUCTION OF
The track will be ballasted, except for the Dehesa del Terzuelo
THE HIGH-SPEED RAILWAY STATION ON THE LOS ARE- The construction of a double track with Iberian gauge, from
tunnel (about 1.5 km), located at the end of the section, which
JOS-NÍJAR STREET, ON THE MURCIA-ALMERÍA LINE OF will be ballastless.
THE MEDITERRANEAN CORRIDOR
These works, with a PEM of 124 million euros, will connect At the beginning of the project, there will be a ballasted con-
these two cities in the southeast of Spain by high-speed rail nection from the conventional line L500 Bif in service. Plane-
in 2026. tario - Valencia de Alcántara (section: Talavera - Monfragüe)
The project includes the construction of numerous structures, to the HSL, as well as subsequent HSL-L500 connections near
including 11 viaducts, 3 of which are large composite decks. the Navalmoral PAL, a PAL currently under construction. The-
The work on the 11 viaducts is a key point in the earthworks se three LAV-L500 connections will require the construction
and determines the execution of various elements of the pro- of a new platform and subsequent track installation, as well as
ject. In this case, of the 7 small viaducts, one is in the final the installation of the connecting track equipment, which will
stage of construction. Of the 3 large viaducts, the foundations interfere with the CMS of the L500 in service.
of 2 are at a very advanced stage. The renewal of the L500 track on the section between the end
buffer stops will also be defined, as this track is necessary for
DESIGN OF THE PLATFORM FOR THE NOGALES DE PISU- the maneuvering of trains to/from the Navalmoral PAL to/from
ERGA-REINOSA HIGH-SPEED LINE. LOT 1. SECTION: ALAR the LAV. The removal of the sections of the L500 that are not
DEL REY AGUILAR DE CAMPO. functionally necessary after the installation of the new con-
This project is part of the development of the Palencia-Santan- nection points will also be included.
der High Speed Line and will provide continuity with the plat-
form project of the Palencia-Aguilar de Campo High Speed
Line. Section: Calahorra de Boedo - Alar del Rey, with the aim In coordination with the project for the future Navalmoral
of improving the efficiency of the national transport system Assembly Base (currently being designed by Esteyco), which
and strengthening territorial cohesion. will centralize the track assembly of the Talayuela - Plasencia
The project covers a length of approximately 14 kilometers, section, the removal of the provisional track defined in that
the main constraints being the topography of the land, the dif- project will be included in the present project to connect the
ferent existing infrastructures (A-67 highway and N-611 natio- L500 to the base, and will include the assembly of the defi-
nal road) and the different urban centers. nitive connecting track and siding of the HSL with the future
maintenance base.
The route will be designed as a UIC gauge (1,435 mm) dual
carriageway with a speed of between 250 km/h and 350 km/h,
depending on the section. The project also includes the transformation of the Plasencia-
Cáceres branch line (L026) into a single-track line with a gau-
Due to the different constraints, 7 structures will be designed ge of 1668 mm, connecting the right track of the HSL (track 2,
with a total length of approximately 930 meters, of which 2 towards Cáceres) with the L536 junction or the removal of the
are pergolas that allow crossing the A-67 highway and the Arroyo de la Herrera - Bif. El Chaparral, giving continuity to
N-611 road, and 6 tunnels with a total length of approximately the high-speed line from Cáceres (Track 1, towards Madrid).
4,000 meters. The project will be carried out using BIM methodology, inclu-
The project will be prepared using BIM methodology, inclu- ding 3D and 4D models of the planned works.
ding 3D and 4D models of the planned works.
330 Anuario del Ferrocarril 2026 Spanish Railway Yearbook