company guide  pansion of La Hoya Station, extensive utility-relocation works.   750-metre-long loops in accordance with the interoperable

                                                                   freight-train standars.
                 Mediterranean Corridor - High-Speed Line between Murcia
                                                                   Refurbishment of the Roda de Bará Tunnel. Mediterranean
                 and Almería section. Totana-Totana section. Railway sub-
                                                                   Corridor standard-gauge conversion.  Adaptation of the
                 structure and civil works. The project comprises a 10-kilomet-
                                                                   Roda de Bará tunnel cross-section for the implementation of
                 re section of the Murcia-Almería High-Speed Line. It involves
                 earthworks, six viaducts (one 954 m long over a motorway),
                                                                   standard gauge. The works include the modification of the
                                                                   clearance envelope for the new gauges, the installation of slab
                 four overpasses, two underpasses, and the construction of a
                 new station in the municipality of Totana.
                                                                   and damp issues, and the installation of an enhanced drainage
                 Madrid-Basque Country-French Border High-Speed Line.
                                                                   system.
                 Pancorbo–Ameyugo Subsection. Railway substructure and   track, structural repairs to the tunnel due to significant leakage
                 civil works. Construction of 8.4 kilometres of high-speed rail-  Works on Line 200 (Madrid-Barcelona) for the Algeciras-Za-
                 way platform, including 5.2 kilometres of tunnels excavated   ragoza railway motorway. Adaptation of 69 overpasses and 8
                 using the New Austrian Tunnelling Method (NATM), and 1.3   tunnels along the section between San Fernando de Henares
                 km of post-tensioned in-situ concrete viaducts, with decks   (Madrid) and Santa María de Huerta (Soria), to achieve the re-
                 executed using different construction methods: launching   quired clearance for transporting lorries by rail using specific
                 gantry, falsework bents and full-support falsework.  rolling stock.

                 Track assembly and storage base of the Murcia-Almería High-  Works on Line 420 (Bobadilla–Algeciras) for the Algeciras–
                 Speed Line. Murcia-Lorca section. Construction of a base for   Zaragoza Rail Motorway. Stabilisation of the slope on the Al-
                 the supply of materials and ballast required for the installation   margen hillside and adaptation of the tunnel clearances along
                 of track on the Murcia-Almería High-Speed Line.   the line, to achieve the required clearance for transporting
                                                                   lorries by rail using specific rolling stock.
                 Track assembly and storage base of the Madrid–Extremadura
                 High-Speed Line. Talayuela–Plasencia section. Construction   Enlargement of the railway sidings at Arcos de Jalón and Si-
                 of a base for the supply of materials and ballast required for the   güenza stations (Line 200, Spain) to 750 meters in order to
                 installation of track on the Madrid–Extremadura High-Speed   accommodate long freight trains.
                 Line.
                                                                   Replacement of sleepers in the Tardienta district. Replace-
                 Valladolid Railway Network.  East Section. Civil and track   ment of 103,000 sleepers along various sections of the San
                 work. Spain. This project comprises a total of 17.5 kilometres,   Juan De Mozarrífar-Selgua route on Line 200 Madrid-Barce-
                 with two branches at the initial section and two temporary   lona.
                 connections to the existing line at both ends. A Iberian-gauge
                 bypass mainly for freight transport will be constructed, where   Emergency works for the replacement of severely damaged
                 a new Railway Complex will be located. The section includes   rail on the Madrid–Atocha Cercanías–Pinto section of Line
                 one viaduct, five underpasses, eight overpasses and a pede-  300 (Madrid–Valencia).
                 strian footbridge. The most unique distinctive structure is the
                 Los Tramposos Viaduct, with a total length of 1,130 metres.  Duplication of  the North-Northwest High-Speed Corridor:
                                                                   RAF Palencia - Vilecha High-Speed Junction section, and
                 Eastern Railway Bypass of Valladolid. Track construction and   electrification of the Palencia - León line on the newly du-
                 electrification. Execution of the track works and the overhead   plication sections. Assembly of the second track on the Las
                 contact line required to provide full service to the Eastern Rail-  Arenas - Vilecha Junction section to complete double-track
                 way Bypass of Valladolid and the logistics facilities located   operation on the Palencia - León line. The works include the
                 within the new Railway Complex.                   electrification of the duplicated sections and the conversion of
                                                                   the current Villada High-Speed Unit into a Train Overtaking
                 Implementation of standard gauge on the Mediterranean   and Parking Facilty.
                 Corridor. Castellbisbal-Murcia Section. Castellón-Vinaroz
                 Subsection. Implementation of standard gauge on the gene-  Sleeper renewal and ballast stripping project on the Madrid–
                 ral tracks along 77.5 kilometres of the section, as well as on   Seville High-Speed Line (Phase 2). Renewal of nearly 124,000
                 station sidings, some of which have been extended to provide   sleepers, including ballast stripping and replacement, over a